Spring Life Private Hospital

From licence to construction.

In progress

Bulk earthworks and bulk infrastructure

Civil works

3 August 2026 to 30 September 2026

Earthmoving, cut-and-fill operations, platforms, stormwater infrastructure, internal roads and preparation for bulk-service connections

Target opening: April 2028

The programme.

Each milestone can be opened to show the work included in that phase.

Approval to develop and operate the proposed 100-bed private hospital

Feasibility and market studies; approved building plans; EIA approval; geotechnical, traffic, electrical and bulk-services studies; land surveying; engineering design and clinical planning

Acquisition of Erf 307, KwaMhlanga B for the hospital development

Site establishment, vegetation removal, clearing, stripping and preparation of the construction area

Finalisation of the required land-use rights for the hospital development

Earthmoving, cut-and-fill operations, platforms, stormwater infrastructure, internal roads and preparation for bulk-service connections

Excavations, reinforced foundations, ground beams, slabs and below-ground services

Structural frame, walls, columns, structural slabs, roofing and building envelope

Internal partitions, ceilings, doors, flooring, wall finishes, joinery and completion of clinical and administrative spaces

Electrical reticulation, backup power, HVAC, lifts, plumbing, fire systems, medical-gas systems and building-management infrastructure

Access roads, parking areas, pedestrian routes, drainage, landscaping, external lighting and final service connections

Installation and testing of medical equipment, ICT systems, furniture, security systems and operational equipment

Final inspections, snagging, compliance certification, staff recruitment and training, operational testing and hospital-readiness activities

Commencement of hospital operations, subject to final certification and operational approvals

Approvals held.

Licence to establish

February 2021

Building plans approved by the Mpumalanga Department of Health

Building plans approved by Thembisile Hani Local Municipality

Title deed transferred

October 2025

Environmental impact assessment approved

Geotechnical investigation completed

Traffic impact study completed

Rezoning finalised

August 2026

Underlying documents are not published and are available under confidentiality.

Next.

Foundations and substructure

1 October 2026 to 15 December 2026

Superstructure

15 January 2027 to 15 April 2027