From licence to construction.
In progress
Bulk earthworks and bulk infrastructure
Civil works
3 August 2026 to 30 September 2026
Earthmoving, cut-and-fill operations, platforms, stormwater infrastructure, internal roads and preparation for bulk-service connections
Target opening: April 2028
The programme.
Each milestone can be opened to show the work included in that phase.
Approval to develop and operate the proposed 100-bed private hospital
Feasibility and market studies; approved building plans; EIA approval; geotechnical, traffic, electrical and bulk-services studies; land surveying; engineering design and clinical planning
Acquisition of Erf 307, KwaMhlanga B for the hospital development
Site establishment, vegetation removal, clearing, stripping and preparation of the construction area
Finalisation of the required land-use rights for the hospital development
Earthmoving, cut-and-fill operations, platforms, stormwater infrastructure, internal roads and preparation for bulk-service connections
Excavations, reinforced foundations, ground beams, slabs and below-ground services
Structural frame, walls, columns, structural slabs, roofing and building envelope
Internal partitions, ceilings, doors, flooring, wall finishes, joinery and completion of clinical and administrative spaces
Electrical reticulation, backup power, HVAC, lifts, plumbing, fire systems, medical-gas systems and building-management infrastructure
Access roads, parking areas, pedestrian routes, drainage, landscaping, external lighting and final service connections
Installation and testing of medical equipment, ICT systems, furniture, security systems and operational equipment
Final inspections, snagging, compliance certification, staff recruitment and training, operational testing and hospital-readiness activities
Commencement of hospital operations, subject to final certification and operational approvals
Approvals held.
Licence to establish
February 2021
Building plans approved by the Mpumalanga Department of Health
Building plans approved by Thembisile Hani Local Municipality
Title deed transferred
October 2025
Environmental impact assessment approved
Geotechnical investigation completed
Traffic impact study completed
Rezoning finalised
August 2026
Underlying documents are not published and are available under confidentiality.
Next.
Foundations and substructure
1 October 2026 to 15 December 2026
Superstructure
15 January 2027 to 15 April 2027